Remodeling of the existing railway infrastructure in order to create the required technical backup facility to support the current railway rolling stock inventory at the Gdynia Grabówek train station.

The Scope of the Works

Building permit level drawings and execution drawings:

  • traction network,
  • energy & power for other individual and business entities and low voltage electrical power,
  • rail traffic control,
  • railway telecommunications,
  • sewage lines.
Project duration

2014

The value of investments

The value of investments corresponding to the scope of the design works:

13,000,000 PLN (3,200,000 EUR)